Kandahar Municipality Initiates Concreting of 3 Sub Roads

In its ongoing development efforts, Kandahar Municipality has commenced the refurbishment of roads by concreting three streets in the fifth district of the city, Gulshan Mina. These streets span 310 meters in length and are 7 meters wide. Construction work commenced a week ago, with the remaining tasks scheduled for completion within three weeks. A […]

In its ongoing development efforts, Kandahar Municipality has commenced the refurbishment of roads by concreting three streets in the fifth district of the city, Gulshan Mina.

These streets span 310 meters in length and are 7 meters wide. Construction work commenced a week ago, with the remaining tasks scheduled for completion within three weeks.

A team of 15 individuals is actively engaged in daily operations to restore these streets, comprising 5 skilled workers and 10 unskilled laborers.