As per the Kabul Municipality’s Program and Project Management Department, the construction of this road segment, which commenced in the month of Saur (Ghoi) this year, has advanced by 31% in accordance with road construction standards and the specified project timeline. The Khairkhana Kotal Road, stretching 2520 meters in length and 60 meters in width […]
As per the Kabul Municipality’s Program and Project Management Department, the construction of this road segment, which commenced in the month of Saur (Ghoi) this year, has advanced by 31% in accordance with road construction standards and the specified project timeline.
The Khairkhana Kotal Road, stretching 2520 meters in length and 60 meters in width with two lanes, has seen the paving of a 2020-meter section following the completion of its foundational part. This upcoming opening to traffic is anticipated to alleviate congestion in the vicinity.
Considered an essential economic corridor and transit route for the country’s 14 northern provinces, this project involves the construction of bridges, culverts, flowerbeds, parking facilities, road markings, lights, traffic signs, and other standard road components. The entire project is projected to conclude by mid-2021.
there is no tags in this article.
دیدگاه بسته شده است.